Advanced Options: "Das Ende der nach dem Statusdatum abgeschlossenen...." doesn't work

    Frage

  • Hello!

    I found this error in the German version of MSP-2010 only:

    After activating the following advanced option(s) "Das Ende der nach dem Statusdatum abgeschlossenen Teile zurück zum Statusdatum verschieben" (English: "Move end of completed parts after status date back to status date") or/and the following 2 options ("Den Anfang der vor dem Statusdatum..." and "Und das Ende abgeschlossener...") I don't see the desired effect within my project plan.

    No matter if I select a status date before or after the task - when I assign say 50% completed to that task, it will show the black progress bar within the task-bar (Gantt-Diagram), but the task won't move a bit.

    My version is: MS-Project Professional 2010 (14.0.6023.1000) SP1 MSO (14.0.6112.5000)

    Does anyone have an explanation/solution for this strange behaviour?

    The English MSP2010 Professional behaves as expected.

    Thanks in advance!

    Tom

    P.S. There is no MS-Project forum category available!... so I have to put it into General