Resourcing Project Management Tasks
-
Dienstag, 22. Mai 2012 10:11
Hi all,
i'm sure this question has been asked, but cannot find it.
I need to add 'project management' tasks that span the complete project duration, and then assign resources to those tasks as a percentage.
How do i create a task that spans the complete project duration?
Alle Antworten
-
Dienstag, 22. Mai 2012 10:42
Found the answer. Searched for 'hammock' tasks
- Als Antwort markiert Julie SheetsMVP, Moderator Dienstag, 22. Mai 2012 17:05
-
Dienstag, 22. Mai 2012 11:05Moderator
Thanks for the feedback!
-
Dienstag, 22. Mai 2012 11:12Nothing worse than somebody finding an answer to their own question and not posting the answer..