Integration Services Install Rolled Back on Upgrade
-
Montag, 3. Dezember 2012 06:48
I had a W2K8 r2 Datacenter host with 7 vms. I upgraded the host to W2k12 Datacenter. All the vms worked correctly except one W2K8 standard VM. When I loaded the new integration services into the W2K8 standard VM, it notified me they were an older version, I went ahead and installed them. Reboot the VM. On startup I get notified that the updates failed, and they are rolled back.
The vm boots up ok and runs fine on the old (w2k8) integration driver. In Hyper-V Manger, for this VM, in the Networking tab it says Status: Degraded (integration services upgrade required).
Should I worry about this? The VM seems to work fine. Any suggested fix? Thanks.
- Bearbeitet Tom in LA Montag, 3. Dezember 2012 07:02
Alle Antworten
-
Dienstag, 4. Dezember 2012 15:59Is the VM running Windows Server 2008 or Windows Server 2008 SP2? SP2 is the supported version.
tim
- Bearbeitet Tim CerlingMicrosoft Community Contributor Dienstag, 4. Dezember 2012 15:59
-
Sonntag, 9. Dezember 2012 10:16The VM is Windows 2008 Standard, service pack 2. I have other VMs running W2K8 sp2 with integration services running properly. It's just this one server/vm that won't upgrade the integration services after I upgraded the host server.