Team Assignment pool in project server 2013

    Question

  • Hi,

    Team Assignment feature in Project Server 2013:

    Is this feature working in PS 2013?

    I have created a resource(Team Leader) and enabled "Team Assignment Pool" option and selected a Team Name in Manage Users.

    Added this resource to resource sheet in the project, inserted "Team Assignment Pool" field and selected "Yes".

    Assigned this resource to three tasks. Saved and Published the plan.

    Mapped  Team Name in manage users for two resources(team members).

    Now, i can see these three tasks only in Team Leader's page not in Team members page.

    Also i do not see "Self-assign Team tasks" option in Tasks page.

    Please help.



    K.Gokulraj

    Sunday, October 06, 2013 6:53 AM

Answers

All replies

  • Hi,

    it does work for me. Is "Self-assign Team Tasks" enabled for group Team Members (your two resources are member of, I assume)?

    Regards
    Barbara

    Monday, October 07, 2013 10:58 AM
    Moderator
  • Please find below the screen shot, i do not see the self-assign team task option. For Team members group "Self-assign team task" option is selected in Global Permission.

    Also i have created a task and assigned it to a resource who is a team resource, i published the plan, that task is not visible in team members task page as well.

    I have created this team resource, assigned him a group(which is created through enterprise custom field), enabled Team assignment pool in his profile.

    Still is not working.


    K.Gokulraj

    Tuesday, October 08, 2013 7:44 AM
  • Hi,

    could you please repost screenshot? I am not able to see. Below a screemshot of my settings:

    IT HW MA1: normal user, member of group Team members. Team Name set.
    IT HW Team, in this case a generic resource, but it does also work for a "normal" resource, I tested that. Team Name is set and Team Assignment Pool is set to YES. This resource has to be used for initial assignment.

    Tuesday, October 08, 2013 7:50 AM
    Moderator
  • Please find attached, i dont see "Resource Team assignments" option.

    K.Gokulraj

    Tuesday, October 08, 2013 11:46 AM
  • Hi,

    This button is only available in Task view.

    Can you see it there?
    Barbara


    Tuesday, October 08, 2013 11:59 AM
    Moderator
  • Hi,

    I am in task view, didn't click the add row.

    Now i can see, it is working thank you.


    K.Gokulraj

    Tuesday, October 08, 2013 1:11 PM
  • Sorry, was mislead by different resolution and smaller icons.

    However, it is working now, fine.
    Barbara

    Tuesday, October 08, 2013 1:56 PM
    Moderator