Is it possible connecting Project 2007 client to Project Server 2010?

Answered Is it possible connecting Project 2007 client to Project Server 2010?

  • Tuesday, April 10, 2012 8:44 PM
     
     

    I cannot connect to Project Server 2010 by using Project professional 2007. Does anybody know if its possible?

    Thanks!

All Replies

  • Tuesday, April 10, 2012 8:48 PM
     
     

    This is the error btw.

  • Wednesday, April 11, 2012 2:08 AM
    Moderator
     
     Answered
    edmaisjm --
     
    The only way that you can connect Microsoft Project 2007 to Project Server 2010 is if your organization upgraded from Project Server 2007 and placed the Project Server 2010 install in Backwards Compatibility Mode (BCM).  From the text of the error message, it appears your system is not running in BCM.  Based on this, I believe you will need to upgrade to Microsoft Project Professional 2010 with all due haste.  Hope this helps.
     

    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

    • Marked As Answer by edmaisjm Wednesday, April 11, 2012 2:07 PM
    •  
  • Wednesday, April 11, 2012 2:07 PM
     
     

    Thanks Dale!

    I've installed a fresh version of Project Server 2010, so I'll have to install project professional 2010 too.

    Thanks very much!

  • Thursday, April 12, 2012 1:49 AM
    Moderator
     
     
    edmaisjm --
     
    You are more than welcome for the help, my friend!  :)
     

    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"