PWA updating wrong for 24 hour calendar tasks

Spørgsmål PWA updating wrong for 24 hour calendar tasks

  • Wednesday, May 16, 2012 10:04 PM
     
     

    Hi, I have a project set with standard calendar from 8am to 5pm. There are few tasks which need to be worked during offshore time. So, for those tasks, I an setting them as 24 hour calendar and Ignore Resource Calendar as 'YES'.

    But, when the resource enter updates in Project server ( PWA ) the updates are coming up wrong. The Actual Finish/Planned Finish times are updated to 11:59PM on the day. Also, the duration is being overwritten as 23.98h. Anyone ran into this kind of error? And if so, what helped?

    Thanks,

    Geeta

      

All Replies

  • Thursday, May 17, 2012 11:40 PM
    Owner
     
     

    Can you give a little more information Geeta please?  What is the resource entering when they make the update?  Just marking them 100% complete?

    Thanks and Best regards,

    Brian.


    Blog | Facebook | Twitter | Posting is provided "AS IS" with no warranties, and confers no rights.
    Project Server TechCenter | Project Developer Center | Project Server Help | Project Product Page

  • Friday, May 18, 2012 3:19 PM
     
     

    Hi Brian,

    The resources are entering the time worked on the task as 4h ( 4 hours ) or 30m ( 30 minutes ). PWA is calculating if the duration is 4h, then marking the task 100% complete. If the task duration is 8h,  then the task is marked as 50% complete and so on.

    Also, we are on MS Project 2007, SP2.

    Please let me know if you need any details. Thanks, Geeta