Custom Project fields not appearing in MSP_Timesheetline_UserViewCF

已答覆 Custom Project fields not appearing in MSP_Timesheetline_UserViewCF

  • Friday, April 27, 2012 10:25 PM
     
     

    Created custom enterprise fields in MS Project 2010 and would like to use SQL Reporting to generate a report with data from these fields. According to Microsoft, any custom fields added are populated in this table for reporting purposes once data is saved, per this article: http://msdn.microsoft.com/en-us/library/ee767688.aspx

    We have entered data in the fields, saved, sent and approved the timesheet, yet none are appearing in the table itself.


    Moss_AZ

All Replies

  • Monday, April 30, 2012 10:51 AM
     
     Answered

    Hi Moss_AZ--

    Did you verify that reporting Timesheet jobs (save/update) is successful in PWA> Server settings> Manage Queue? Try updating the timesheet again & verify the queue jobs.

    Is this is successful, the data should get updated in Reporting database & _UserView of timesheet should get the data.

    Here is an excellent  sample by Christophe,
    http://blogs.msdn.com/b/chrisfie/archive/2010/04/06/project-server-2010-timesheet-custom-fields.aspx


    Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82

    • Marked As Answer by MOSS_AZ Tuesday, May 01, 2012 11:39 PM
    •  
  • Tuesday, May 01, 2012 11:40 PM
     
     
    Thanks, that link helped. I think the key was to make sure I was in the custom timesheet view when submitting the timesheet. I also noticed in the queue there was a failed job due to a problem with a custom field.

    Moss_AZ


    • Edited by MOSS_AZ Tuesday, May 01, 2012 11:40 PM
    •