Hi John--
You can replace the Generic resource with an enterprise resource using the MS project. You may not be able to replace by Task basis.
Here is the detailed article:
http://office.microsoft.com/en-us/project-help/add-resources-to-your-project-HA010377762.aspx
When you're ready to replace generic resources with actual enterprise resources, you can use the
Build Team dialog box again from, MS project. You can also use the
Resource Substitution wizard. Once you replace generic resource with actual enterprise resource, the tasks wherever the generic resource was assigned to the tasks, the enterprise resource will have those tasks assigned.
Does that help?
If you found this post helpful, please “Vote as Helpful”. If it answered your question, please “Mark as Answer”. Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82