How to hold back timesheet approval until all task updates are approved??

    Question

  • Hii,

    i have heard about this thing,but dont know how to do this??

    How to hold back timesheet approval until all task updates are approved??

    AND ALSO CAN ANY ONE SUGGEST ME GOOD LINKS OR ARTICLES ON TIME AND TASK MANAGEMENT AND APPROVAL IN PROJECT SERVER 2010

    Thursday, July 12, 2012 10:47 AM

Answers

  • Anuj,

    • Yes, Timesheet Managers can approve timesheets, independently of the Status Managers Approval ( if the check box you mention is not enabled). 
    • Timesheets are mainly used to keep track of billable/non billable or project/admin time hours, mainly to be able to use the information for connecting to other billing systems (or at least supply the data). The Timesheets are more controlled and reliable source of information in that context. Status Updates are mainly to keep the project progress updated.
    • I am not sure of what you mean by "Task Status Manager Approval Field". Could you please elaborate.

    In Summary, it will boil down to the process you are wanting to use. The main reason people use the Timesheet Line Approval flag is to avoid confusion. For example, a Timesheet could get approved but then the PM could decide that a task update needs to be rejected. This creates a discrepancy between timesheet data and task data. So if your process mandates no discrepancy, then you should select that check box.


    Prasanna Adavi, PMP, MCTS http://thinkepm.blogspot.com

    • Marked as answer by anuj astro Thursday, July 12, 2012 4:30 PM
    Thursday, July 12, 2012 2:10 PM

All replies

  • Hi Anuj,

    Please see the below article form Technet & Blogs:
    http://technet.microsoft.com/en-us/projectserver/hh147175.aspx
    http://blogs.msdn.com/b/project/archive/2009/11/23/time-tracking-in-project-server-2010.aspx

    Best practice of submitting & reporting actual work
    http://technet.microsoft.com/en-us/library/hh694531.aspx

    For you r question: How to hold back timesheet approval until all task updates are approved??

    If you are using the SEM, Please see imesheet settings & default section in PWA server settings, You have option "Require line approval before timesheet approval "which specifies that each line must be approved before the whole timesheet can be approved. If you only want to approve whole timesheets (no line-by-line approval), select Disable the option.

    Hope that helps


    If you found this post helpful, please “Vote as Helpful”. If it answered your question, please “Mark as Answer”. Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82

    Thursday, July 12, 2012 11:41 AM
  • hi amit,thanx for your response,

    i have one doubt,if i enable task status manager approval but do not select that check box"Require line approval before timesheet approval",then in that case,will time sheet manager be able to approve time sheet without status manager approval,or status manger has to first approve status updates,only then timesheet manager can approve timeshhet??


    • Edited by anuj astro Thursday, July 12, 2012 12:27 PM
    Thursday, July 12, 2012 12:26 PM
  • Hi Anuj,

    They should be but I have not tested it. Since disabling the option, will not check for any line item which is approved or not, Timesheet Manager should be able to approve.
    Would suggest to test the same on Testbox & validate.

    Hope that helps.


    If you found this post helpful, please “Vote as Helpful”. If it answered your question, please “Mark as Answer”. Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82

    Thursday, July 12, 2012 12:36 PM
  • hi amit,

     if i select task status manager approval,but disable that line approval,and if the timsheet manager will be still be  able to approve without status manger approval,then what's the purpose of Task status manager approval,

    hope that you have understand my doubt

    i want to know that what is the exact purpose of task status manger approval field,and what will happen if if select this option with line approval and when i select this without line approval,


    Thursday, July 12, 2012 12:47 PM
  • Anuj,

    • Yes, Timesheet Managers can approve timesheets, independently of the Status Managers Approval ( if the check box you mention is not enabled). 
    • Timesheets are mainly used to keep track of billable/non billable or project/admin time hours, mainly to be able to use the information for connecting to other billing systems (or at least supply the data). The Timesheets are more controlled and reliable source of information in that context. Status Updates are mainly to keep the project progress updated.
    • I am not sure of what you mean by "Task Status Manager Approval Field". Could you please elaborate.

    In Summary, it will boil down to the process you are wanting to use. The main reason people use the Timesheet Line Approval flag is to avoid confusion. For example, a Timesheet could get approved but then the PM could decide that a task update needs to be rejected. This creates a discrepancy between timesheet data and task data. So if your process mandates no discrepancy, then you should select that check box.


    Prasanna Adavi, PMP, MCTS http://thinkepm.blogspot.com

    • Marked as answer by anuj astro Thursday, July 12, 2012 4:30 PM
    Thursday, July 12, 2012 2:10 PM
  • hi prassana

    thanx for response,i was talking about the option "Require Task Status Manager Approval",which is under timesheet settings and defaults under server settings

    my question is  if i select task status manager approval,but disable that Require line approval before timesheet approva checkboxl,and if the timsheet manager will be still be  able to approve without status manger approval,then what purpose will Task status manager approval option will  with that line approval check box disabled will serve

    Thursday, July 12, 2012 4:39 PM
  • That's a real good question Anuj. Here is what I can come up with as an answer:

    • With SEM enabled, the Timesheet line updates will always go to the PM for approval as status updates. You can make them "required" or not, at that point.
    • Without SEM, you can disable task updates going to the status manager, and have timesheets be stand alone data collection items. Otherwise, you can enable task updates approval, and thsi will send the updates to the Status Manager for approval.

    Prasanna Adavi, PMP, MCTS http://thinkepm.blogspot.com

    Thursday, July 12, 2012 6:48 PM
  • thanx prassana for your response,

    but my doubt is still not cleared,

    will the time sheet manager will be able to approve timesheet,if status manager has rejected task updates(with SEM enabled) if i have enabled the option Require Task Status Manager Approval,but disable that  Require line approval before timesheet approval check box


    Friday, July 13, 2012 4:41 AM