Use an Enterprise Custom Date field Gantt chart bar From/To date field in MS Project/ Project Server/Project Online RRS feed

  • Question

  • Want to use an Enterprise Custom Date field (Say 'Current Date') in Gantt chart bar From/To columns in MS Project/ Project Server/Project Online. It doesn't seem possible. Is there any way except changing in every individual project.


    sandeep



    Wednesday, June 5, 2019 6:29 AM

Answers

  • Hi Sandeep,

    You can just use local field in the bar style. Thus you need to customize IN THE TEMPLATE date1 (local custom field) with a formula (=today), then customize your bar style. So every time a new project is created using the template, it will have the local custom date1 and the bar style. Note that it won't apply for the existing projects.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller

    Wednesday, June 5, 2019 7:06 AM
    Moderator