MS Project Issues & Risk - add related item problem RRS feed

  • Question

  • Need some help..

    Currently I am having a problem with issues & risks, every time I try to relate a task to the Issues & risks it doesn't show the list of the task that I want to relate. 

    is there a specific configuration for that?

    KINDLY SEE SCREENSHOT BELOW FOR SAMPLE SCREENSHOT

    Friday, October 11, 2019 5:31 AM

All replies

  • If you look at the Tasks list via the normal UI on that site, it it empty? On the PWA Settings > Enterprise Project Type settings under Synchronization do you have "Sync SharePoint Tasks Lists" enabled?

    Paul


    Paul Mather | Twitter | http://pwmather.wordpress.com | CPS | MVP | Downloads

    Friday, October 11, 2019 7:49 AM
    Moderator
  • If you look at the Tasks list via the normal UI on that site, is it empty? No, I can see the content of the project.

    As per checking it is not yet checked then I turn it on. Question does it have a propagation time? As of now it is not yet showing.

    Friday, October 11, 2019 8:11 AM