Multiple Critical Path RRS feed

  • Question

  • Project plan is structured for multiple WBS / Summary Tasks for different locations.

    How can I see the critical path for each location?

    Friday, June 7, 2019 8:54 AM

Answers

All replies

  • Hi Scatterworlds,

    Each schedule only has a single critical path by definition, unless you want to utilise a master project (which contains multiple single projects).  A quick look on google will provide you with information on master projects, and multiple critical paths therein.


    Ben Howard [MVP] | web | blog | book | downloads | P2O

    Friday, June 7, 2019 9:33 AM
    Moderator
  • There is an option for multiple critical paths in MSP, below is the snapshot of the same. can it help in any way. Else what is it designed for ?


    Friday, June 7, 2019 12:15 PM
  • Well, if you truly have separate independent networks then of course it will work as per the image 1st image.   As soon as you create dependencies between the networks as per the 2nd image then it doesn't. You need to be very aware of how your plan is structured.


    Ben Howard [MVP] | web | blog | book | downloads | P2O

    Friday, June 7, 2019 12:27 PM