identifying & trending Primary, Secondary, and tertiary critical & driving paths RRS feed

  • Question

  • We're looking at new requirements that would require the identification and trending of month-to-month changes based on the primary, secondary, and tertiary critical path as well as driving paths. 

    Due to the number of schedules impacted, we'd be leaning towards methods that we could automate.  

    We're currently on Project Server 2010 but will be migrating/converting to Server 2016 (possibly 2019) in the near future.

    Any thoughts and ideas would be greatly appreciated,

    thanks in advance.

    Dan