Forecasted Start, Finish and Duration RRS feed

  • Question

  • What all factors drive the following of a Task, Summary Task and Project

    1. START 

    2. FINISH

    3. DURATION 

    Thursday, June 6, 2019 2:22 PM

Answers

  • The start date is the start of task.  It can be calculated or set.

    Duration is the time estimate to complete. 

    Finish date is the Start Date + Duration.


    Michael Wharton, Project MVP, MBA, PMP and a Great Guy <br/> Website http://www.WhartonComputer.com <br/> Blog http://MyProjectExpert.com contains my field notes and SQL queries

    Friday, June 7, 2019 1:45 AM
    Moderator

All replies

  • The start date is the start of task.  It can be calculated or set.

    Duration is the time estimate to complete. 

    Finish date is the Start Date + Duration.


    Michael Wharton, Project MVP, MBA, PMP and a Great Guy <br/> Website http://www.WhartonComputer.com <br/> Blog http://MyProjectExpert.com contains my field notes and SQL queries

    Friday, June 7, 2019 1:45 AM
    Moderator
  • There are other factors like constraints ...is there a sequential checklist as how management should interpret while looking at the finish date of a activity / project