none
Resource has work but Peak = 0 RRS feed

  • Question

  • Entry table of the resource sheet view shows 0 peak even though the resource has work.

    Resource graph shows peak OK.

    What do you reckon?

    Resource Name Peak Work
    Mechanical Technician 01 100% 888.5 hrs
    Mechanical Technician 02 100% 227 hrs
    Mechanical Technician 03 100% 1 hr
    Mechanical Technician 04 0% 6 hrs
    Mechanical Technician 05 0% 4 hrs
    Mechanical Technician 06 0% 14 hrs
    Mechanical Technician 07 0% 8 hrs
    Monday, January 13, 2020 2:28 AM