Asked by:
Unexpected behavior in task scheduler jobs on Windows server 2012 R2

Question
-
Hi All,
we Could see Unexpected behavior in task scheduler jobs on Windows server 2012 R2. we have multiple schedule task jobs configured on the server. Each job has more that 2 triggers on different times.
Recently, few schedule task jobs behavior is weird and these running out of the trigger schedule time/sometimes runs twice on same time. Its not for all the jobs only few jobs behaving like that.
Could you please suggest if any idea on this to troubleshoot further to fix the issue.
All replies
-
Hi,
Just try the following methods:
- Check the Scheduled Task is Enabled;
- Check the Scheduled Task’s Conditions;
- Select the Run with Highest Privileges Option;
- Verify the User Account;
- Check Last Result column;
- Make sure to select Run whether user is logged on or not option;
- Change task arguments;
- Make sure that your system is up to date;
- Run Fix My Task Scheduler.
More specific details you could refer to the following link:
https://windowsreport.com/windows-scheduled-tasks-not-running/
Note: This is a third-party link and we do not have any guarantees on this website. This is just for your convenience. And Microsoft does not make any guarantees about the content.
Have a nice day!
Best regards,
Kiki Shi
Please remember to mark the replies as answers if they help.
If you have feedback for TechNet Subscriber Support, contact tnmff@microsoft.com.- Proposed as answer by Kiki ShiMicrosoft contingent staff Monday, November 11, 2019 1:28 AM
-
Hi,
Was your issue solved?
If the reply helped you, please remember to mark it as an answer.
If no, please reply and tell us the current situation in order to provide further help.
Best Regards,
Kiki Shi
Please remember to mark the replies as answers if they help.
If you have feedback for TechNet Subscriber Support, contact tnmff@microsoft.com. -
Hi tnmff,
Thanks for the inputs. we have 100 of the jobs scheduled on the server. But we are having issue with only 5 jobs. Each job has multiple triggers which it needs to run. But sometimes its ran twice on the trigger time or sometimes it runs out of the triggered schedule time.
we need to fix this unexpected behavior of these tasks.
CHANDU
-
-
Hi,
Just try you uninstall the 5 jobs which have issues and rebuilt them, check if it works.
Have a nice day!
Best Regards,
Kiki
Please remember to mark the replies as answers if they help.
If you have feedback for TechNet Subscriber Support, contact tnmff@microsoft.com. -
-
Hi,
Well, since you have done what I mentioned, kindly feedback this situation via Feedback Hub app, I am also going to submit this case to Microsoft.
Or you could open a support request for deep study.
https://support.microsoft.com/en-gb/hub/4343728/support-for-business
Thanks for your understanding and cooperating.
Best Regards,
Kiki
Please remember to mark the replies as answers if they help.