none
Advanced Settings RRS feed

  • Question

  • Gostaria de saber se é possível setar um valor em uma das coluna do project para que sempre que eu adicionar uma linha nova ao projeto este valor apareça automaticamente?
    Thursday, August 8, 2019 12:03 PM

All replies

  • Hi,

    A google translation from portugese gave me the following request:

    "I wonder if it is possible to set a value in one of the project column so that whenever I add a new row to the project this value will automatically appear?"

    We would need more information, but basically I understand that you want to have a task custom field with a default value. So yes it is possible, you can create a custom field at task level with a default value. The field can be text, number, lookup table, date...


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller


    Thursday, August 8, 2019 12:13 PM