  • Hi,

    In MS Project server, there is an option to add Team details for resources. If that is done, the resources in the team can assign tasks to themselves. There is also another option called Resource Groups.

    Can someone please explain the difference between Resource Groups and Team Resources and suggest then best use of the same.

    Thanks,

    Roshni.

    Donnerstag, 17. Mai 2018 05:46

Antworten

  • Hi,

    The resource group is synchronized while using AD sync, this is a AD user's parameter.

    Teams are used if you want to assign tasks to teams. Then users belonging to teams can auto assign the team tasks to themselves in the timesheet process.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller

    Donnerstag, 17. Mai 2018 13:50
    Moderator

Alle Antworten

  • Hi,

    The resource group is synchronized while using AD sync, this is a AD user's parameter.

    Teams are used if you want to assign tasks to teams. Then users belonging to teams can auto assign the team tasks to themselves in the timesheet process.


    Hope this helps,