Project 2013 - administration of workers and machines

    Frage

  • Hello,

    I’m testmanager in a lab.
    I have to plan the workers as well as the testing machines.

    I have a limitied number of workers and a limited number of testmachines.
    The test duration should be determined by the availability of the worker and the testmachines.

    I read both resources should be “work” type.

    And here is my Problem:
    If both are “work” and I assign both of them to the Task, the Duration will be wrong.
    It’s like two man working on a Task….

    Any idea how to get rif of this?

    Thanks!