Progress Bar Not Showing

    Frage

  • Hello All,

    I'm having problems getting my progress bar to show. In Bar Styles, I have a named Progress, with Show For...Tasks:  Drop Down "In  Progress"

    From: Scheduled Start

    To: Physical % Complete

    I definitely want to keep the Physical % Complete, and the duration needs to activate the finish as it is increased.

    Thanks for the help

    Project 2013

    Mittwoch, 9. Mai 2018 20:14

Alle Antworten

  • GUZZLR --

    You need to change the To value back to CompleteThrough, which is the default value.  The progress bar will then show the % Complete for the task.  Physical % Complete would only be relevant if you are entering task progress using the actual Physical % Complete column, which I suspect you are not.  Hope this helps.


    Dale A. Howard [MVP]

    Mittwoch, 9. Mai 2018 22:06