MS Project 2010: How to influence cost column with filter on other columns? RRS feed

  • Frage

  • Dear all,

    I try to filter my task table on a customer column. That works fine, but there is no affect on the cost and work column sum on the whole project. What I want to do is to assign each task to a category (customer column) and then filter on this column to which affect on the project costs happens without  categories.

    Thanks for help!


    • Bearbeitet Gerrit L. _ Donnerstag, 25. April 2013 06:45 Add Tool
    Donnerstag, 25. April 2013 06:40

Alle Antworten

  • Hi Gerrit,

    out of the box it is not possible to calculate the cost column in dependency of a custom filter. In addition to the filter you have to create a custom task cost column with a formula. As formula you take the function IIF(....) in which you define when the costs should be calculated.

    In a similar German Project post I have demonstrated this scenario with screenshots:

    http://www.office-loesung.de/ftopic590098_0_0_asc.php#2491137

    I hope, this will answer your question.

    Best Regards,

    Bernhard Fischer


    Bernhard Fischer [MVP] | www.wodey.de