MS Project 2010: totalling budget cost in resource usage time-phased view. RRS feed

  • Frage

  • Hi all,

     

    I’m trying to modify the time-phased pane in the resource usage view to show the different costs vs. the corresponding budgets. Therefore a particular grouping is applied which structures the costs:

     

    overall personnel costs = costs for internal personnel + costs for external personnel

    overall costs = personnel costs + material costs + investments + …

     

    Now, I’ve defined for each of these cost types (personnel, material, investments,...) a budget resource.

    In the time-phased pane of the resource usage view the above described cost types are aggregated to overall costs. In comparison to these costs i want to show the aggregation of the different budgets to an overall budget. Unfortunately the corresponding line in the time-phased pane remains empty.

    Does anybody know how to activate this aggregation, or are further descriptions/ explanations required?

    Best regards

    Philipp

     