Project Server 2013: Hammock Tasks/ Speed of update within a local project plan RRS feed

  • Frage

  • Dear Forum,

    i'm using the feature of hammock tasks within a local project plan. I have ~15 of these tasks and 15+1 milestones that are used to define start and finish of the hammock tasks. Currently my observation is that updating the hammock tasks takes quite long: it takes between 10 and 30 seconds (on a notebook with 3GHz and 8 GB RAM, WIN 8.1) to transfer the milestone changes to the hammock tasks. There are resources assigned to the hammock tasks.

    Is there a way to accelerate the updating of the hammock tasks?

    Thank you for your feedback and kind regards

    Philipp

    Mittwoch, 6. August 2014 07:22

Antworten

  • Hi Philipp,

    no, we have no special accelerator for calculating hammock Tasks. The only thing what you can do is to update your Project Pro with the actual CU and/or use the 64 Bit Version of Project.

    In some cases we have performance issues in both the Server and the Client. In addition there are a lot of bugs which were fixed in the past. The actual Version No is 15.0.4641.1001.

    You can find the latest updates there:

    Best Regards

    Bernhard Fischer


    Bernhard Fischer [MVP] | www.wodey.de