we are using MS Project Server 2007. Here is my issue: For one specific project we do not want to capture the overtime work cost of resources. That means if they work 10 hours the project should calculate the costs of 8 hours. I tried to create a calendar
among several other things, but apparently you cannot define an Hours Per Day value for each resource individually. MS Project can only specify a single Hours Per Day value at the project level. But the resources does not want to book overtime on
My Task page (double work). So how I can fix this problem with the tool?