Open the closed tasks RRS feed

  • Question

  • Dear all,

    When the manager close task to update, and publish. the task will no longer be available in My work, tasks again for update.

    How to open the closed tasks and assign to employees again?

    Thanks all.

    Saturday, June 2, 2012 3:44 PM

Answers

  • DoLeVu --
     
    You need to go back to the Close Tasks to Update page in PWA, deselect the Lock checkbox for uncompleted tasks, and then publish the project again.  My question is why you closed tasks to update when those tasks were not completed in the first place.  You need to reserve using the Close Tasks to Update feature for only completed tasks.  Hope this helps.
     

    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

    • Marked as answer by DoLeVu Sunday, June 3, 2012 7:43 AM