[PS 2010] - Default task custom field value not set when adding new task from My Task RRS feed

  • Question

  • Hi,

    I have found that after approving a new task that is being added via My Task, the default value for the task custom field does not get populated to the newly created task. Is this a bug? I am using the latest Jun CU.

    Regards

    Gan

    Wednesday, July 25, 2012 3:16 AM

All replies

  • Hi Gan

    refer the following question by piotrso. I think you have the same question.

    Force enterprise custom field to set default value on adding new task

    And as Wim said 

    "You can fill in the values afterwards and you can even see in the task details what you changed, but the value is not entered by default."

    I hope it will help you.


    Manish

    Wednesday, July 25, 2012 4:42 AM
  • Hi Manish,

    Thanks for your reply. However my question is whether this is a bug or not. If this is indeed a bug then we should highlight it to Microsoft.

    Regards

    Gan

    Wednesday, July 25, 2012 5:50 AM
  • Gan

    Yes, I understtod what you mean

    I think it should be counted as a bug. (or something on which has to be worked on).

    :-:


    Manish

    Monday, July 30, 2012 5:53 AM