Task Settings and Display >> Tracking Method (Disabled) RRS feed

  • Question

  • Dear All,

    I am not able to change the below tracking method in the Project Online Tracking method under the Task and Settings and Display.

    --------------------------------------------------------------------------------------------------------------------------

    (UnSelected) Percent of work complete. Resources report the percent of work they have completed, from 0 through 100 percent. 
    (UnSelected) Actual work done and work remaining. Resources report the actual work done and the work remaining to be done on each task. 
    (Selected) Hours of work done per period. Resources report their hours worked on each task per period. 
    (UnSelected) Free form. Resources report their hours using any method 

    --------------------------------------------------------------------------------------------------------------------------

    Note: I am the administrator for the environment.

    Thank you.


    -SNKBalaji


    • Edited by SNKBALAJI Monday, May 8, 2017 6:58 AM
    Monday, May 8, 2017 6:58 AM

Answers

  • Hi,

    you can't use the first two options, if Single Entry Mode (SEM) is enabled in PWA Settings - Timesheet Settings and Defaults.

    SEM requires "Hours of work done per period".

    Does that help?
    Barbara

    • Marked as answer by SNKBALAJI Monday, May 8, 2017 10:58 PM
    Monday, May 8, 2017 8:36 AM
    Moderator

All replies

  • Hi,

    you can't use the first two options, if Single Entry Mode (SEM) is enabled in PWA Settings - Timesheet Settings and Defaults.

    SEM requires "Hours of work done per period".

    Does that help?
    Barbara

    • Marked as answer by SNKBALAJI Monday, May 8, 2017 10:58 PM
    Monday, May 8, 2017 8:36 AM
    Moderator
  • Thank you So much Barbara for the details.


    -SNKBalaji

    Monday, May 8, 2017 10:58 PM