Portfolio Analysis with resources (2013) RRS feed

  • Question

  • Hi,

    Is it possible to use a Resource Plan for each project in the portfolio analysis instead of assignments (nominative resources or generic resources) on tasks ?

    Thanks

    Monday, August 3, 2015 4:46 PM

Answers

  • Hi,

    For that, you have to set in the resource plans that the capacity is calculated from the resource plan and not the project plan.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller |

    • Marked as answer by WLID1966 Tuesday, August 4, 2015 8:35 AM