locked
Default Working days are changing to half days in Project 2016 RRS feed

  • Question

  • Hi,

    I have set default working days to 09:00 to 12:00 and 13:00 to 17:00.

    When i add a day off for some of my users, save and reopen it displays the other days they are working as half days- 09:00 to 12:00? 

    This seems to happen randomly not user specific and can change from day to day?

    Using Project standard 2016 fully patched and Office pro plus 2013 fully patched

    thanks

    Thursday, January 18, 2018 12:16 PM

All replies

  • Make sure that the enterprise calendar times with the times found in Project Pro options. 

    Michael Wharton, MVP, MBA, PMP, MCT, MCTS, MCSD, MCSE+I, MCDBA
    Website http://www.WhartonComputer.com
    Blog http://MyProjectExpert.com contains my field notes and SQL queries

    Friday, January 19, 2018 4:10 AM
  • Sorry "enterprise calendar" cannot find this option? it it the Servers calendar?

    Thanks

    Thursday, January 25, 2018 4:04 PM