none
Linked task between master- and sub project RRS feed

  • Question

  • Is it possible to link a task from subproject to a task in master project?- Solved

    Best regards Rune Larsen


    • Edited by Redda Joppe Wednesday, January 30, 2019 9:44 AM
    Tuesday, January 29, 2019 1:08 PM

Answers

All replies

  • Hi,

    that can be done. Do you see any issues?

    Regards
    Barbara

    Tuesday, January 29, 2019 1:30 PM
    Moderator
  • how do i do the linking as shown in your project Predecessors?

    


    Best regards Rune Larsen

    Tuesday, January 29, 2019 1:41 PM
  • Hi,

    the easiest way is to use den Link button in ribbon after selecting dependent tasks.

    To enter Predecessors manually the path to the other project and the TaskId, e.g. C:\Users\<user>\Desktop\Main.mpp\1 in my sample: Predecessur of "a" is "x", "x" has number = 1 in C:\Users\<user>\Desktop\Main.mpp.

    If you are working with Project Server or Project Online, the path will be different. Just Link one task using the menu to see how it looks like.

    • Proposed as answer by Tom BoyleBPC Wednesday, January 30, 2019 1:04 PM
    Tuesday, January 29, 2019 2:59 PM
    Moderator
  • Hi

    thank you. this works. 


    Best regards Rune Larsen