Task not assigned to resource after project publish RRS feed

  • Question

  • Hi,

    I have created project, add resource and publish project. problem is that project resource not getting and project and task. when user click on task tab on PWA site NO task are show.

    pls guide what could be an issue and how to fix it.

    thx


    iffi

    Wednesday, May 31, 2017 8:13 AM

All replies

  • Hi,

    I'd say you have a couple of things to check first:

    • is the resource looking at the right time period in the "task" page versus the assignment in MS Project?
    • is there any filter activated in the task page view?
    • did you check in the queue if the publish job was successful?
    • in MS Project, in the column "publish" set to YES for the given tasks?
    • is the assignment owner configured as the resource itself in MS Project for the given tasks ?
    • is the booking type set to committed?
    • have you checked that you assigned in MS Project the resource from the enterprise resource pool, and not a local resource?

    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller

    Wednesday, May 31, 2017 11:47 AM