locked
Multiple CM 2007 into 1 2012 Primary site RRS feed

  • Question

  • Our current archetexture includes multuple primaries under a centeral site in 2007 r2. Based on the organizational structure, and enhancments to Primary sites and DPs in 2012, I would like to simplify everything to one primary site. Is that doable? Can I migrate the centeral and all of the primaries into a single 2012 Primary site?

    Monday, August 26, 2013 9:29 PM

All replies

  • Absolutely yes, and you should as well...

    SCCM 2012 was designed/built for having a single primary in the first place... (even though you can extend to more sites if you have more than 100.000 clients).

    In my last two migration projects we migrated several CM 2007 primaries (with a hierarchy) to a single CM 2012 primary (no hiearchy).

    / Johan


    Regards / Johan Arwidmark Twitter: @jarwidmark Blog: http://www.deploymentresearch.com FB: www.facebook.com/deploymentresearch

    Monday, August 26, 2013 10:36 PM
  • Yes, I echo Johan's statements and can't stress this enough, having a single primary site in ConfigMgr 2012 is preferred and highly recommended (unless you find a real technical reason not to have one which there truly only is one: 100,000+ clients). A primary site in 2007 is not the same thing or used for the same thing as a primary site in 2012.

    Jason | http://blog.configmgrftw.com

    Monday, August 26, 2013 11:31 PM