Can i Define Timesheet periods for different departments RRS feed

  • Question

  • Hi,

    I need to define two timesheet period each for one department in Project server 2010. One department wants to submit time sheets weekly and the other wants to submit monthly.

    Thanks in Advance

    Regards 

    Deepak D

    Tuesday, September 16, 2014 6:32 AM

All replies

  • Hi Deepak,

    The Time Reporting periods are not linked with the departments and they are set per project server instance. Maybe the department that wants to submit the timesheet on a monthly basis can use multiple timesheets for the month (4-5) but you need to look at the overlaps (e.g. 29/Sep - 05/Oct). An option in this case would be to use the last Saturday/Sunday of the month as month's end

    Hope this helps

    Paul

    Tuesday, September 16, 2014 8:25 AM