Disjoin the servers from the existing farm, rejoin them to a new farm RRS feed

  • Question

  • Hi folks,

    While i am searching about Move Sharepoint Farm servers to another AD domain  i found one line like - disjoin the servers from the existing farm, rejoin them to a new farm.

    Please let me clear how it will work disjoin and rejoin and how i will do changes  ?

    Thanks

    Tuesday, July 14, 2015 5:47 AM

Answers

  • Hello Jio333,

    that means you need first to remove the server from the Farm - Central Admin->System Settings->Manage servers in this farm, next to the server you want to move/remove is a link "Remove Server"

    When the server is not part of the SP farm any more you have to disconnect it from the domain, join it to the new domain and run PSConfig to join it to the new SP farm.