Daily work data on ms project RRS feed

  • Question

  • Dear All,

    How to put below detail:-

     Start 4/11/2017   6hr machine work

    5/11/2017     No work

    6/11/2017      No work due to technical problem

    7/11/2017      7hr40min

    How to set as above calendar provide brief detail? 

    Thursday, November 9, 2017 9:53 AM

All replies

  • Vishwas --

    You would need to do the following to enter the Actual Work data shown in your example:

    1. Apply the Task Usage view and zoom the timephased grid to show the Days level of detail.
    2. Right-click anywhere in the timephased grid and select the Actual Work details on the shortcut menu.
    3. Scroll the timephased grid to 4/11/17.
    4. In the Actual Work cell on 4/11/17 for the resource row, enter 6h.
    5. Scroll the timephased grid to 5/11/17.
    6. In the Actual Work cell on 5/11/17 for the resource row, enter 0h.
    7. Scroll the timephased grid to 6/11/17.
    8. In the Actual Work cell on 6/11/17 for the resource row, enter 0h.
    9. Scroll the timephased grid to 7/11/17.
    10. In the Actual Work cell on 6/11/17 for the resource row, enter 6.33h.
    11. Double-click the name of the task and then apply the Notes page in the Task Information dialog.
    12. Enter a note to explain why no work was performed on 5/11/17 and 6/11/17.
    13. Click the OK button.

    Hope this helps.


    Dale A. Howard [MVP]