  • When synchronizing the MPP file with the ShPt task list, we have seen tasks re-sorting in the MPP file.  Very annoying, especially with schedules with a large number of tasks.  Just wondering if anyone has experienced this issue, and if you could point me in the right direction for solving it.  FYI, listing below my signature the columns we are synchronizing (in case you know of an issue with one or more of these).

    FYI, we are using MS Project 2013 Pro and SharePoint 2010.  We tried using the synch feature with MSP 2010 and it did not seem to be available.

    Greatly appreciate your help on this topic.  Sincerely,

    Michael.

    ------------------------------------------------------

    Columns to map:

    • Text30
    • Text15
    • Baseline Start
    • Baseline Finish
    • Duration
    • Baseline Duration
    • Baseline Work
    • % Work Complete
    • Flag8
    • Critical
    • Number5
    • Text19
    • Work
    • Actual Start
    • Actual Finish