Project Server 2010 Excel Reports RRS feed

  • Question

  • For the last few weeks I have tried to create an Excel timesheet report. However, the data that is being pulled will not go past May. Timesheets have been submitted and approved for this project. The project is saved, published and checked in. The resources on the project continue to submit time against that the tasks, however the timesheet report does not reflect any reported time after May.

    LaKysha

    Wednesday, August 13, 2014 2:01 PM

All replies

  • Hi,

    I guess you are reporting against the Timesheet OLAP cube? If yes, check if the OLAP DB has been correctly generated.


    Hope this helps,


    Guillaume Rouyre, MBA, MCP, MCTS |

    Wednesday, August 13, 2014 2:15 PM
    Moderator
  • Hi LaKysha,

    You can create your excel reports creating a connection directly to PWA_Reporting Database, may this help, because if you connect via OLAP you need to check first if your cube is running, and your Project Info for a cube depends how you configure your builds for OLAP.

    Ray


    • Edited by Ray Chapa Monday, August 18, 2014 2:34 PM
    Monday, August 18, 2014 2:32 PM