  • Dear All,

    we are using PWA 2013 for scheduling and logging time, we are a media agency with lots of running projects.

    when i access the resource availability, for a selected period, I see all the projects that the resource worked on including those with no current assignments or done, so they are showing 0hr.

    i need to know if there is a way to filter those in a way to show only the projects with allocated time for the period selected.

    the below is a screen shot of what i am viewing, i need all the projects with 0h not to show.

    thank you in advance.

    Resources availabilty


    Traffic Coordinator Born Interactive

    Tuesday, November 19, 2013 8:12 AM

All replies

  • Hello AsaadSaleh,

    I believe this is by design. You can however create a custom report to show anything you need.

    Best regards,

    René Alvarez


    Rene Alvarez

    Wednesday, November 20, 2013 7:36 AM
  • Thank you Rene,

    can you share or guide me to a report showing the tasks done by resources during a specific period of time?

    i was not able to get that done, 

    what i can do is a report that will give me all the tasks the resources worked in but the totals are for the specified period thus i need to open it in excel and filter the non zero values.

    i'm sure there should be an easier way?


    Traffic Manager Born Interactive

    Wednesday, November 20, 2013 2:36 PM
  • Thank you Rene,

    can you share or guide me to a report showing the tasks done by resources during a specific period of time?

    i was not able to get that done, 

    what i can do is a report that will give me all the tasks the resources worked in but the totals are for the specified period thus i need to open it in excel and filter the non zero values.

    i'm sure there should be an easier way?


    Traffic Manager Born Interactive

    Wednesday, November 20, 2013 2:38 PM
  • AsaadSaleh,

    Are you using Project Server on premises or Project Online?

    The approach will be different between them.


    Rene Alvarez

    Wednesday, November 20, 2013 3:13 PM