none
Even though the weekend time sheets are grayed out as Non working days , users are able to enter their actuals on those days and able to submit . How to fix this? RRS feed

  • Question

  • Even though the weekend time sheets are grayed out as Non working days , users are able to enter their actuals on those days and able to submit . How to fix this?

    

    Tuesday, July 4, 2017 2:34 AM

All replies

  • Hi Charansai,

    There is no way to prevent this.  The timesheet presents what the user is planned to work and then allows the user to enter when they worked, and this could include a weekend.  If a user makes a mistake in their timesheet and they do not see it, the timesheet manager can reject the timesheet.


    Ben Howard [MVP] | web | blog | book

    Tuesday, July 4, 2017 6:09 AM
    Moderator
  • Hi,

    sorry to tell. This is just how it works. System does not prevent users to work on weekends.

    A workaround with some effort: create 2 periods per week, one for Monday to Friday, one for Saturday to Sunday. Set all weekend periods to "Closed". Not sure if your requirement is important enough to spend this effort???

    Regards
    Barbara 

    Tuesday, July 4, 2017 6:11 AM
    Moderator
  • The above comments above are true, however this can be managed by the resource manager rejecting the timesheet.


    Michael Wharton, MVP, MBA, PMP, MCT, MCTS, MCSD, MCSE+I, MCDBA
    Website http://www.WhartonComputer.com
    Blog http://MyProjectExpert.com contains my field notes and SQL queries

    Tuesday, July 4, 2017 2:09 PM
    Moderator