none
I cannot add the Resource Department to the OLAPPortfolioAnalyser RRS feed

  • Question

  • Hi,

    In this page : http://msdn.microsoft.com/en-us/library/ee767696.aspx I can read :

    "If the Project Departments custom field and Resource Departments custom field are configured to accept multiple values of the Department lookup table, those custom fields are not shown in the Available fields lists."

    My Project Departments and Resource Departments fields are not set to accept multiple values. So actually I can add the Project Department field to the OLAPPortfolioAnalyser cube, but I cannot add the Resource Department. Why?

    Thanks for your help

    Thursday, July 7, 2011 2:23 PM

Answers

  • Go to Server settings

       OLAP Database Management

         select cube and click on CONFIGURATION

          on the CUBE DIMENSION, Select RESOURCE cube, select DEPARTMENT and copy to other site.

    PS also check it may already be there.  It looks like "Resource Departments_Resource"

     

    Cheers


    Michael Wharton, MBA, PMP, MCT, MCSD, MCSE+I, MCDBA
    www.WhartonComputer.com
    • Marked as answer by WLID1966 Thursday, July 7, 2011 7:49 PM
    Thursday, July 7, 2011 4:47 PM
    Moderator