Resource Allocation % RRS feed

  • Question

  • I’ve set up my task and I’m tracking by duration (allocated), Actual duration, Remaining duration. I’ve been my start, finish dates and I have resources assigned.

    On one task I have four people working 100% with 2000 hours allocated. When I change the to 50% I would expect to see some change in the amount of time it will take them to finish, but instead I see no change. 

     

    Friday, May 5, 2017 12:53 PM

All replies

  • tnewton2060 -

    Is your Task Type value set to Fixed Duration for this task?  If so, the Duration will not change.  Please let us know and we will try to help you.


    Dale A. Howard [MVP]

    Friday, May 5, 2017 1:37 PM
    Moderator
  • My task type value is not set to Fixed Duration, but my Duration doesn't change. What I would like to see is I change the four resources to 50% the Finish Date moves to the right or out so they finish later.
    Monday, May 8, 2017 8:38 PM
  • tnewton2016 -

    Is the task Auto Scheduled?  Please let us know and we will try to help.


    Dale A. Howard [MVP]

    Monday, May 8, 2017 10:09 PM
    Moderator
  • The task is not Auto Scheduled because Project keeps changing dates erroneously. I don't have predecessors assigned either.
    Monday, May 15, 2017 4:43 PM