How to display Work in days (PWA 2010) RRS feed

  • Question

  • Hi,

    How to display Work in days instead of hours in the Prject Center (PWA 2010) ?

    Thanks

    Wednesday, October 5, 2011 3:49 PM

Answers

All replies

  • Clcik in My Tasks

    From ribbon click on Units and select Work>>Days 

    Thanks,

    Hrishi

    Sr Consultant , DeltaBahn LLC

     

    Wednesday, October 5, 2011 5:39 PM
    Moderator
  • WLID1966 --

    It is not possible to format the Work field in days rather than hours in the Project Center view in PWA.  Hrishi's answer is correct, but only for the Tasks page in PWA.  Hope this helps.


    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

    • Marked as answer by WLID1966 Wednesday, October 5, 2011 7:56 PM
    Wednesday, October 5, 2011 7:43 PM
    Moderator
  • Thanks Dale,

    I expected to create my own "Work in days" column with a custom field and a formula. But this custom field doesn't agregate at the group level : I want to display the project total work summed up at a first group level and then at a second group level. But at these group level my formula doesn't display anything.

    What did I miss?

    Thanks.

     

    Wednesday, October 5, 2011 8:02 PM
  • WLID1966 --

    I do not believe that custom Project fields shown in Project Center views will roll up the way you want them to do.  Sorry.  Hope this helps.


    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

    • Marked as answer by WLID1966 Thursday, October 6, 2011 4:22 PM
    Thursday, October 6, 2011 3:36 PM
    Moderator
  • ;-(

    Thanks a lot!

    Thursday, October 6, 2011 5:25 PM