1 Email shows all tasks assigned to team member RRS feed

  • Question

  • Hi,

    Project Server 2013, (not using timesheets)
    Can any ways I can accumulate all the 10 tasks assigned to user xyz,
    and send him 1 email containing all tasks info to the users.

    2nd- Can I send a email to every users- with their Pending tasks of last week-in 1 email.

    Thanks

    Monday, March 9, 2015 6:36 PM

Answers

  • Hi,

    I think the easiest way of doing that is to have a report configured with reporting services and deliver it via email using a report subscription

    Hope this helps

    Paul


    • Edited by PaulMarinescu Monday, March 9, 2015 7:30 PM
    • Marked as answer by mafab Monday, March 23, 2015 5:51 PM
    Monday, March 9, 2015 7:28 PM

All replies

  • Hi,

    I think the easiest way of doing that is to have a report configured with reporting services and deliver it via email using a report subscription

    Hope this helps

    Paul


    • Edited by PaulMarinescu Monday, March 9, 2015 7:30 PM
    • Marked as answer by mafab Monday, March 23, 2015 5:51 PM
    Monday, March 9, 2015 7:28 PM
  • I would first decide if that is worthwhile. My experience is that very quickly canned emails like that get treated as spam and sent straight to the bin.

    It is useful info, but when thrown at people, it is rarely received well!


    Rod Gill
    Author of the one and only Project VBA Book
    www.project-systems.co.nz

    Monday, March 9, 2015 7:36 PM
    Moderator
  • Hi Rod,
    My present situation is Email notification is based on every individual Task.
    So for 10 tasks-I gets 10 emails- as of present case.

    What I want is- 1 single Email- which summarizes all 10 tasks for that day- from Task Center.

    So what Paul says- Is we needed SSRS report - and report subscription service.

    Please suggest- anything else not possible out of box of project server 2013.


    • Edited by mafab Tuesday, March 10, 2015 7:05 AM spell correction
    Tuesday, March 10, 2015 7:05 AM
  • Its definitely a custom solution. You can do it via VBA or a SSRS report or any other reporting tool but you are more limited if this is Project Online. If on prem then can read data directly from the reporting db using VBA.

    Rod Gill
    Author of the one and only Project VBA Book
    www.project-systems.co.nz

    Wednesday, March 11, 2015 9:21 PM
    Moderator