Project Server 2013 how to get cost data for resource based on month RRS feed

  • Question

  • Hi all,

    I do know that there are some default view in Project Server 2013 PWA which show the cost data for resources and tasks. However, I would like to get the resource cost data per month. Where can i find it? Any suggestion is highly appreciated!

    Regards,

    Anna

    Thursday, August 7, 2014 3:28 AM

All replies

  • Hi Anna,

    You can't have in PWA a view such as the resource usage view in MS Project Pro which can give you the cost per assignment by time periods.

    I'd suggest to create a report for that, either in Excel Services or in SSRS.


    Hope this helps,


    Guillaume Rouyre, MBA, MCP, MCTS |