linking projects tasks are not reflecting after change dates in one project task RRS feed

  • Question

  • 2 projects are link . in which one project task is link with another project task. and first project task is predecessor of another project task when we change the date of first project task . it is not reflecting the 2nd project task date.

    This is very serious problem.

    how it is resolve.

    Thursday, April 18, 2013 7:08 AM

All replies

  • Hi John,

    Are the tasks automatically or manually scheduled?

    Is the successor constrained?

    Does the successor have an actual start date?

    Thursday, April 18, 2013 9:22 AM
    Moderator
  • Hi,

    And what's more, are both projects open simultaneously?

    Greetings,

    Thursday, April 18, 2013 10:26 AM
    Moderator
  • Yes both projects are open simultaneously
    Thursday, April 18, 2013 10:39 AM
  • John.Eddie --
     
    Pardon me for bumping into this thread, but you did not answer the questions asked of you by Julie Sheets.  Would you please answer her questions so that we can help you?

    Dale A. Howard [MVP]

    Thursday, April 18, 2013 12:14 PM
    Moderator