Task Deadline Indicator Does Not Function in PWA RRS feed

  • Question

  • MS Project Professional 2013 has a great indicator that shows when a task has gone beyond it's deadline. That indicator does seem to work in PWA 2013. Should it??? I added the indicator in the GANTT chart (down arrow). Does something need to be configured? With the reduction in purchases of Project Pro to reduce costs and using PWA more and more, that sure would help! 

    Jay W. Ahearn, PMP, MCP

    Friday, May 30, 2014 6:14 PM

All replies

  • If you are talking about the Red Diamond indicator that appears besides the task in MS Project professional, then it is not available in PWA.

    The down arrow is available in PWA. Make sure you are selecting the right Gannt Chart format for your specific view.

    And finally, a custom indicator could be easily built with a formula against deadline, if that is what you needd.


    Prasanna Adavi,PMP,MCTS,MCITP,MCT http://thinkepm.blogspot.com

    Friday, May 30, 2014 7:56 PM