Is it possible to create a Network Diagram that displays red,green, yellow... RRS feed

  • Question

  • Hi

    A client prefers to see a Network Diagram.  

    Is it possible to display tasks in a Network Diagram in color (red, green, yellow) based on a formula ...i.e. if tasks are late, on time, etc.?

    I am using project 2010

    Thank you,


    Sunday, August 11, 2013 10:49 PM

All replies

  • Actually I think I found a technique.  I edited the box style and added the field I use on the gantt chart view that displays the stop light status.  I had to apply that to each network box, which was a pain in 2007.  I will try it in 2010 next. :)

    Any suggestions are welcome.

    Thank you

    Sunday, August 11, 2013 11:29 PM