Can't assign resources to tasks RRS feed

  • Question

  • Hi.

    I can't assign resources to tasks in Project Server 2010.

    The weird thing is the resources are visible in the Resource Sheet although when trying to assign them to tasks the drop down simply doesn't work: it's empty. I've also try to check the Build Team From Enterprise and it is also empty regarding the project team.

    It was working fine till yesterday, when we've made a migration of the SQL to other server in order to improve our EPM performance. We've also disabled the compatibility mode.

    Is it related? Can you please help?

    Thanks in advance!

    Marisa

     

     

     

    Wednesday, September 21, 2011 5:31 PM

Answers

  • Hi.

    We've have solved it! :)

    It seems having to do with the compayibility mode.

    Project plans need to be saved into Project Server with Project 2010. Once it is saved when opening again, the resources are now available to assign.

     

    Thank you guys! :)

     


    Marisa
    Thursday, September 22, 2011 3:26 PM

All replies

  • So, can you add them to the project using Build Team?  If so, can you assign them using other methods (eg the Assign Resources UI, the Task form, or the task or resource usage view?)
    Ben Howard [MVP] blog | web
    Wednesday, September 21, 2011 6:20 PM
    Moderator
  • Can you stop the previous SQL Instance and see if there is any error occuring.

    What are the steps you have followed to move the databases to the new server?


    Ravishankar
    Thursday, September 22, 2011 4:46 AM
  • Hi.

    We've have solved it! :)

    It seems having to do with the compayibility mode.

    Project plans need to be saved into Project Server with Project 2010. Once it is saved when opening again, the resources are now available to assign.

     

    Thank you guys! :)

     


    Marisa
    Thursday, September 22, 2011 3:26 PM