Tallying only the Work-type Costs RRS feed

  • Question

  • How would I separately tally the work-only costs in a project that had tasks with mixed resources (both work and cost types)?  I know I can do it at the Resource Sheet (cost table) level, but that's for the entire project.  What I really need is for it to happen at the task level.  Ideally, I could look at the Cost Table in the Task View, and see a column that lists and tallies only the work types of assignments.  Not sure if there's an easy built-in way to do it, or if it would involve custom fields and formulas.

    (using Project Professional 2013 on a Win7 computer)

    Friday, May 3, 2013 1:31 AM

All replies

  • You could do that in the Resource Usage view, group by Resource Type and then Task....or something like that.

    Andrew Lavinsky [MVP] Blog: http://azlav.umtblog.com Twitter: @alavinsky

    Friday, May 3, 2013 2:23 AM
    Moderator