"Software Development Plan" template in Project Pro 2013 RRS feed

  • Question

  • Hi,

    How can we build a view like this one with something which looks like a report in the upper part of the screen, and the Gantt Chart in the lower part ?

    Thanks

    Saturday, November 23, 2013 9:47 AM

Answers

  • The view is exactly as you describe.  The upper part of the view is a report using a bar chart showing Scheduled Duration.

    Once the report is created, go to the View ribbon and in the Split View group, select Details checkbox to show the Gantt chart in the lower pane.

    While on the View ribbon, click "Other Views", and select Save View.

    • Marked as answer by Robert6156 Monday, November 25, 2013 5:43 PM
    Saturday, November 23, 2013 3:07 PM
    Moderator

All replies

  • The view is exactly as you describe.  The upper part of the view is a report using a bar chart showing Scheduled Duration.

    Once the report is created, go to the View ribbon and in the Split View group, select Details checkbox to show the Gantt chart in the lower pane.

    While on the View ribbon, click "Other Views", and select Save View.

    • Marked as answer by Robert6156 Monday, November 25, 2013 5:43 PM
    Saturday, November 23, 2013 3:07 PM
    Moderator
  • Hi,

    Software development plan is a form of project plan, which includes Scope plan, Schedule plan, Quality plan, Risk plan and Procurement plan.


    Thanks!!